Quality control

Every work activity carries its own check.

Not one quality register for the whole site, but a checklist attached to the item you estimated — what to inspect before the work, what to watch while it runs, and what to verify after, with HOLD points that stop sign-off until an engineer clears them.

One checklist, as it opens in the app QC Master → Concrete Work → Column Concreting
QC Master — Concrete Work · Column
Column concreting
IS 456:2000 · Premium · B 11 · S 20 · P 24
Before — the pour has not started
Column setting-out and size verified against the grid / structural drawing before shuttering Drawing · Column axis within ±6 mm of grid line; section size ±3 mm Hold
Reinforcement verified — diameter, number, lap length, stagger, tie spacing and binding IS 456:2000 · Compression lap ≥ 45d and staggered; ties per drawing ±15 mm, 135° hooks Hold
Formwork checked for plumb, dimensions, rigidity and adequate props and bracing IS 456:2000 · Plumb within 6 mm or H/1000 per storey, 12 mm overall Hold
Base cleanout completed and starter / kicker verified before pour Good practice · Base free of debris and water; kicker 75–100 mm, true to line Standard
Pre-concreting inspection / pour card approved by the engineer Pour card signed off for rebar, cover, formwork, cleanout and readiness Hold
During — concrete is going in
Concrete placed with limited free fall via tremie or chute — no segregation IS 456:2000 · Free fall ≤ 1.5 m; drop chute for taller lifts Standard
Placed in layers and compacted with a needle vibrator, without over-vibration IS 456:2000 · Layers 300–450 mm; needle penetrating the previous layer about 100 mm, withdrawn slowly Basic
Test cubes cast at the required frequency during the pour IS 516 · 150 mm cubes sampled per IS 456 Cl. 15.2.2, cured and identified Basic
Concrete and ambient temperature controlled — hot-weather precautions IS 7861 · Placing temperature preferably ≤ 30 °C; chilled water, evening pour or retarder Premium
After — the concrete is in place
Formwork stripped only after the minimum stripping period, without arris damage IS 456:2000 · Column vertical faces after 16–24 h with OPC (Table 11) Hold
Continuous curing of the column for the minimum required period IS 456:2000 · ≥ 7 days moist curing for OPC; 10–14 days for PPC / PSC Basic
4 of 5 holds cleared 11 of 24 points shown here
Every line above is a real checkpoint out of the app's own library, with its IS code and its acceptance criterion. Nothing here was written for this website.
Step 2 of the chain

Nine parts that turn a checklist into a quality system.

A checklist on its own is a form. What makes it a system is the moment it is tied to, the point at which it can stop the work, the standard it is judged against, and the fact that the bill has to wait for it.

01 · The library

84 checklists, across all fifteen trades, on the day you install it.

Most quality software gives you a blank checklist builder and wishes you luck. This one ships with the checklists already written — more than five hundred individual checkpoints, each one carrying the standard it comes from and the tolerance that decides pass or fail.

Work categoryThe checklists it ships with
Earth Work / ExcavationSite Clearing & Setting Out · Foundation Excavation · Anti-Termite Treatment (Pre-construction) · Earth Filling & Compaction · Sand / Murrum Filling · Soling / Sub-base
Concrete WorkPre-Concreting Pour Card (HOLD) · PCC / Levelling Course (M10) · Footing / Raft Concreting (M25) · Column Concreting · Beam Concreting · Slab / Roof Concreting · Concrete Sampling & Cube Testing (HOLD)
ReinforcementBar Bending Schedule / Cutting & Bending · Cover & Spacer Check · Column / Beam Reinforcement · Slab Reinforcement · Lap / Development Length (HOLD)
Formwork / ShutteringFormwork — Footing / Column · Formwork — Beam / Slab · De-shuttering / Stripping Time (HOLD)
Brick Work / MasonryAAC / Concrete Block Work · Stone Masonry · Half-Brick / Partition Wall
Plaster WorkInternal Plaster — 12 mm · External Plaster — Double Coat · Ceiling Plaster · POP / Gypsum Punning
PaintingPutty & Primer — Surface Prep · Internal Emulsion Paint · External / Weatherproof Paint · Enamel Paint — Wood / Metal · Distemper / Texture
Flooring WorkVitrified / Ceramic Tile Flooring · Marble / Granite Flooring · Kota / Natural Stone Flooring · Skirting & Dado · IPS / Cement Flooring · Chequered Tile / Paver Block
Wood & PVC WorkDoor Frame (Chaukhat) Fixing · Door Shutter — Flush / Panelled · Window / Ventilator Fixing · UPVC / PVC Door & Window · Door Hardware & Fittings
Steel & Aluminium WorkStructural Steel Fabrication & Welding (HOLD) · Steel Erection / Bolting · Aluminium Door / Window / Glazing · ACP Cladding / Structural Glazing · MS Railing / Grill / Gate · Roof Truss / Purlin
Plumbing WorksWater Supply Piping + Pressure Test (HOLD) · Drainage / Soil & Waste Piping · Sanitary Fixtures Installation · External Sewer / Manhole · Septic Tank / Soak Pit · Water Tank — Overhead / Underground · Rainwater / Storm Water
Electrical WorksConduit Concealing — Slab / Wall · Wiring & Insulation / Megger Test (HOLD) · Switchboard / DB Installation · Earthing (HOLD) · Light Fixtures / Fans / Accessories · Panel / Cable Laying
Water ProofingFoundation / Retaining Wall WP · Toilet / Wet-Area WP + 48 h Ponding (HOLD) · Terrace / Roof WP — APP Membrane · Water Tank WP · Basement WP
Roofing WorkRCC Roof Slab Finishing & Treatment · Sheet Roofing — GI / Colour-coated · AC / Fibre Cement Sheet · China Mosaic / Brick-bat Coba
MiscellaneousBoundary Wall / Compound · Road / Paving / Kerb · Material Receipt Inspection (MIR) · Snag / Pre-Handover Inspection · Safety & Housekeeping

Alongside these sit seven broader starter checklists — one each for concrete, reinforcement, formwork, masonry, earthwork, waterproofing and general work — for the site that wants one sheet per trade rather than one per activity.

A standard behind every line

Each checkpoint carries the code it comes from — IS 456, IS 516, IS 1199, IS 2502, IS 1786, IS 2720, IS 6313, SP 34 — and the tolerance that settles the argument. "Plumb within 6 mm or H/1000 per storey" is not a matter of opinion between two engineers.

Tied to the mix, not just the trade

Eighteen of the checklists are linked to a specific recipe in Quantity Master — M10 Concrete (1:3:6), M25 design mix, Internal Plaster 12 mm, Vitrified Tile Flooring, APP Membrane. Pick that formula on a Measurement Book item and the app suggests the checklist that belongs to it.

Yours to change

Every checklist is editable — add a checkpoint your client insists on, delete one that does not apply to your work, mark a point as a HOLD, or write a whole new checklist for a trade nobody else does. What ships is a starting point, not a cage.

Deleting one keeps it deleted. The library is planted once, not re-seeded on every restart. If your team removes a checklist because it does not apply to how you build, it does not quietly come back the next time the app updates.
02 · Before, during and after

A form filled at the end is a record. A checklist tied to the moment is a control.

Most site quality registers are signed after the work, because that is when somebody has time. By then half of what mattered is buried in concrete. Here every checkpoint is tagged to the moment it can actually be checked, and the checklist opens in three parts.

One column pour, in three parts

This is the Column Concreting checklist, split the way the app splits it. Read the "before" column and ask yourself how many of those you could still verify at four o'clock, after the pour.

Before — while it can still be fixed
  • Setting-out and size against the grid — axis within ±6 mm, section ±3 mm.
  • Reinforcement — diameter, number, lap ≥ 45d and staggered, tie spacing, 135° hooks.
  • Clear cover on all faces — 40 mm ±5 mm for a column, blocks at 1 m centres, four a face.
  • Formwork plumb within 6 mm or H/1000 per storey, props and ties rigid, no bulge.
  • Slump and grade for each load — within ±25 mm of the approved value.
  • Pour card signed by the engineer before concrete starts.
During — while it is happening or never
  • Free fall ≤ 1.5 m, tremie or drop chute on a taller lift, no segregation at the base.
  • Layers of 300 to 450 mm, needle in vertically, penetrating the previous layer about 100 mm, withdrawn slowly, stopped at the cement sheen.
  • No cold joint — each layer placed before the one below takes its initial set.
  • Cubes cast at the sampling frequency, labelled, and the slump logged against the batch.
After — what the work has to survive
  • Stripping time — column faces after 16 to 24 hours with OPC, arrises undamaged.
  • Honeycomb and voids inspected on the stripped face and repaired with approved non-shrink grout.
  • Curing continuous for 7 days with OPC, 10 to 14 with PPC or PSC.

The cover you cannot check twice

Clear cover is the single biggest reason an RCC member fails early in India. It is checkable for about twenty minutes — after the concrete goes in, it is unverifiable for the life of the building. So it is a "before" point, and it is a HOLD.

That is the whole argument for tagging a checkpoint to a moment. The engineer who opens the checklist at 9 a.m. sees six things he must clear before the pour and nothing else. He is not scrolling past curing and stripping questions that make no sense yet.

The three parts collapse and expand, so a supervisor working the pour sees only the "during" list on his phone.
Stripping and curing sit in "after", and stay open on the activity until somebody actually clears them — they do not vanish when the pour is signed.

It hangs off the estimate, not off a separate register

The checklist is picked on the Measurement Book item itself. When you type the heading and the app fills the clause, the unit, the rate, the category and the material formula, it also suggests the checklist for that work — matched from the heading, the clause text and the concrete grade.

So the quality record is attached to the same line that the BOQ prices, the programme schedules and the bill is raised against. There is no second list of activities to keep in step.

How an item is set up
03 · HOLD points

A HOLD point is where the work stops and waits for a person.

This is the difference between a checklist and a quality system. A normal checkpoint is a thing you confirm. A HOLD point is a thing that stops the activity: work must not continue until the QC engineer physically checks it and approves it. Over a hundred of the checkpoints in the library are marked HOLD.

Nine checklists carry HOLD in their own title, because the whole activity is a gate:

01
Pre-Concreting Pour Card
Formwork, rebar, cover, embedments, joint preparation, mix design, vibrators and curing — signed before a single load arrives.
02
Concrete Sampling & Cube Testing
Sampling frequency per IS 456, cubes cured in water, 7-day and 28-day results recorded, a failure raises an NCR.
03
Lap / Development Length
The check nobody wants to make after the shuttering is closed.
04
De-shuttering / Stripping Time
Stripping early is free today and expensive for thirty years.
05
Water Supply Piping + Pressure Test
Tested before the chase is closed and the wall is plastered.
06
Toilet / Wet-Area WP + 48 h Ponding
Forty-eight hours of ponding, cleared before the screed goes on top of it.
07
Wiring & Insulation / Megger Test
Insulation resistance proved before the boards are handed over.
08
Earthing
Earth pit and resistance verified, not assumed.
09
Structural Steel Fabrication & Welding
Weld and fabrication clearance before erection.
hold

Marked in red, everywhere it appears

A HOLD carries a red marker on the card in QC Master, on the phone at the pour, and on the printed checklist that goes into the file. Its tooltip says exactly what it means, in one sentence, so a new site engineer is never guessing:

Mandatory inspection. Work must stop at this point and cannot continue until the QC engineer physically checks and approves it.

A HOLD cannot be levelled away. Whatever depth of checking you have chosen for a project, every HOLD point stays in the list. Marking a checkpoint critical automatically puts it in the minimum set — the software will not let you configure a hold point out of existence.

And on the phone, it asks

If the site engineer tries to approve an inspection with holds still unticked, the app stops him and says so — 3 HOLD point(s) are not ticked. Approve anyway?

It is a question, not a lock. A supervisor standing in the rain with a truck waiting can still approve — and the record then carries, permanently, which holds were open when he did. That is a deliberate choice: an app that cannot be overridden gets worked around, and then you have no record at all.

04 · Basic, Standard, Premium

One checklist. Three depths. You choose how hard to check.

A boundary wall and a hospital do not deserve the same quality effort, and a checklist long enough for the hospital gets ignored on the boundary wall. So every checkpoint carries a level, and the levels are cumulative — Basic is the minimum a site must check, Standard adds the working controls, Premium is the full set including the laboratory work.

Column concreting, at each level

The same checklist reads 11 points, 20 points or 24 points. Nothing is a different list — the shorter ones are the longer one with the deeper checks hidden.

Basic — 11 points, the minimum
  • Setting-out and size against the grid, reinforcement and lap, cover blocks, formwork plumb, slump for each load, the signed pour card, layered placing with the vibrator, cubes cast, stripping time, curing. Every HOLD point is here, by rule.
Standard — 20 points, the working default
  • Adds base cleanout and the 75–100 mm kicker, mould oil and sealed joints, the RMC challan checked for grade, batch time and haul, free fall through a chute, no cold joint, plumb re-checked mid-pour, a batch-wise register of slump and cube IDs, and honeycomb repaired on the stripped face.
Premium — 24 points, the full set
  • Adds embedments, dowels and column-to-beam junction bars positioned before the pour, and concrete temperature control under IS 7861 — placing at 30 °C or below, with chilled water, an evening pour or a retarder in hot weather.

Set once for the project, overridden where it matters

Each project carries a default quality level, chosen when the project is created. Every item in the Measurement Book inherits it, and its Quality Level box simply reads Project default (Standard).

Where one item deserves more, you override it on that item alone. A Standard project with its transfer beams and its water tank set to Premium is a perfectly normal way to run a job — and it takes two clicks, not a second checklist.

The card header shows the count at each level — B 11 · S 20 · P 24 — so you can see what you are choosing before you choose it.
Switching the level changes what is shown, never what exists. Move a project from Standard to Premium in the last block and the deeper points appear on every checklist at once.

Why cumulative matters

If Basic, Standard and Premium were three separate lists, they would drift. Someone would correct a tolerance in one and not the others, and after a year nobody would trust any of them.

Here there is one list with a level on each line. Correct a tolerance once and it is correct at all three depths, on every project, from that moment.

05 · How to do this work

The checklist says what to check. This says how to do it.

A young engineer sent to inspect a work he has never seen done cannot judge it. So every checklist carries a How to do this work button, and behind it a CPWD-aligned method statement — the reference, the materials, the numbered procedure, and the precautions.

Method of work — column concreting

CPWD Specifications 2019, Vol. 1 — RCC Columns

Materials and equipment

Design-mix concrete Cube moulds Needle vibrator Tremie / chute

Procedure

01
Check the column formwork for plumb on both faces and the cleanout at the base.
02
Confirm the reinforcement, lap and cover, then close the cleanout.
03
Check the slump and grade of the delivered concrete.
04
Place the concrete through a tremie or chute, keeping free fall under 1.5 m.
05
Vibrate each layer with a needle vibrator; avoid displacing the cage.
06
Cast cubes and continue the pour without a cold joint.

Precautions

  • Pour at a controlled rate so the form is not overloaded.
  • Keep the cover blocks in place while vibrating.

A method for every activity, not for the famous ones

All 84 checklists carry one. The anti-termite method tells the man with the sprayer to dilute to the specified concentration and treat the bottom of the excavation at five litres a square metre. The earth-filling method tells him to spread in 200 to 300 mm layers, water to near optimum moisture, compact and test each layer before the next one goes on.

References are at CPWD section level — CPWD Specifications 2019, Volumes 1 and 2, and the CPWD General Specifications for Electrical Works — and the procedures follow standard CPWD and IS practice.

  • Editable, like everything else. The method has its own boxes in the checklist editor — reference, materials, steps and precautions, one per line — so your own way of doing a work becomes the method your site reads.
  • It prints with the checklist. The signed checklist for an activity goes into the file with its acceptance criteria and its method statement attached.
  • It is also in Hinglish, because the person who most needs to read a method statement is often not the person who reads English.

Half of site quality is not carelessness. It is a supervisor who was never shown the right way once, and has been doing it his way for eleven years.

The checklist and method as a printed document
06 · English and Hinglish

The man doing the checking may not read English. He still has to use it.

Every checkpoint, every acceptance criterion and every method statement is written in Hinglish as well — Hindi in Roman letters, with the technical words kept in English, the way a site actually talks. One toggle in the toolbar switches the whole library over.

EnglishHinglish
Formwork checked for verticality and plumbWithin tolerance on both faces Formwork ki verticality / plumbDono faces par tolerance ke andar
Reinforcement, lap and cover verifiedAs per drawing Reinforcement, lap aur cover verify kiDrawing ke hisaab se
Concrete placed via tremie or chute, no segregationFree fall less than 1.5 m Concrete tremie/chute se placed, koi segregation nahiFree fall 1.5m se kam
No cold joint, continuous pourPour rate maintained Koi cold joint nahi, continuous pourPour rate maintain ki
Method step: Vibrate each layer with a needle vibrator; avoid displacing the cage. Method step: Har layer ko needle vibrator se vibrate karo; cage displace mat karo.
Precaution: Keep the cover blocks in place while vibrating. Precaution: Vibrate karte waqt cover blocks apni jagah rakho.

Only the words change

IS codes, grades like M25, units, dimensions and the HOLD marker stay exactly as they are in both languages. A tolerance of ±25 mm is a tolerance of ±25 mm — it does not need translating, and translating it would be a good way to create an error.

Search works in both

The checkpoint search reads the Hinglish text as well, so an engineer typing "vibrator" or "cover blocks" finds the card whichever language he is looking at it in.

Where it stops, honestly

The Hinglish is written for the 84 checklists that ship with the app. A checklist your own team writes stays in the language they typed it in — the toggle falls back to English for it rather than pretending to translate.

07 · At the pour

The whole checklist opens on the phone, with no signal.

A quality check that has to be carried back to the office and typed up is a quality check that happens on Friday for the work of Tuesday. The site app puts the same library in the engineer's hand at the pour — the real checklist, not a simplified version of it.

  • Pick the activity from the list, grouped by work category exactly as it is on the desktop.
  • Checkpoints arrive already grouped Before, During and After, each with its acceptance criterion under it, and HOLD points in red.
  • Tick each point and add a remark against the ones that need one — "honeycomb at north face, chipped and repaired".
  • Record the location and the verified quantity — F1, 2.700 cum — so the inspection lands against the right item.
  • Photographs with the latitude, longitude, accuracy and time burnt onto the image itself. A photo with the coordinates printed on it is evidence; a photo in a WhatsApp thread is not.
  • It all queues on the phone when there is no network and goes up the moment there is one. A basement or a remote site does not stop the record.
Everything the site app does

It lands on the activity, not in an inbox

The inspection syncs against the same Measurement Book item that the BOQ priced and the programme scheduled. Nobody has to match it up afterwards, and nobody can quietly file it against the wrong pour.

Each person sees only what you allow. Access is granted project by project and module by module, read or write. A supervisor can record a QC inspection without ever seeing a rate or a bill.
Offline is the normal case, not the exception. The app is built assuming the network is not there, because on most sites it is not.

Who actually uses it

The site engineer and the supervisor tick the checklist. The consultant or PMC sees the same record to certify against, with a read-only view where that is all he should have. The contractor sees which of his work has cleared its check and which has not.

What each party gets
08 · Quality before payment

Work that has not passed its check can be held back from the bill.

This is the one thing that makes a site take quality seriously, and almost no quality software does it, because the quality tool and the billing tool are usually two different products from two different companies. Here they are the same file.

How it behaves when the bill is raised

When items are pulled into a running-account bill, each one is checked against its own quality status first. An item that has been inspected and approved goes in. An item still waiting for its check is left out, and the app tells you which and why — reported as skipped — QC pending, not silently dropped.

Cleared, and billable
The item has passed its QC approval and moved on through the workflow — approved, synced to the programme, billable or already billed. It goes into the bill.
Not cleared, so not billed
The item is still in the workflow before QC approval. It is reported as skipped, with the reason, and the certified amount for that bill is the work that actually passed.
Never entered the workflow at all
An item with no quality record — older work, or a job you never put under the gate — is allowed through. Switching this on does not freeze the bills you are already running.

The same check applies whether you are billing a sub-contractor or raising a running-account bill on your client, because both read the same measured item.

What this changes on a site

The day a sub-contractor works out that an uninspected pour does not appear in his running account, he starts asking for the inspection himself. Quality stops being the engineer chasing the contractor, and becomes the contractor chasing the engineer.

Nothing about that requires a new process. It is the same measurement, the same checklist and the same bill you were already raising — with one condition put between them.

The signed checklist, its acceptance criteria and its method statement print as a document you can put in the client's file, next to the bill it released.

And on the programme

A quality check is not only a gate on money. The same item drives physical progress and earned value, so an activity that is built but not cleared is visible as work done and not yet certified — which is exactly the position a project manager needs to see before a review meeting, not after it.

Planning and progress

Open the checklist for your own next pour.

Thirty minutes on a call. Tell us the work you are running this week and we will open its checklist, its hold points and its method statement while you watch.